The programmed dates for progression of the scheme are as follows:

Phase 1: Overall Project Planning

Complete

Phase 2: Constraints Study

Complete

Public Consultation II (Constraints and Route Corridors)

20 th April 2001 & 10th May 2001

Publish Constraints Study Report

June 2001

Phase 3: Route Selection

 

Public Consultation III (Preferred Route)

27th to 31st May 2002

Finalise Route Selection Report

Autumn 2002

Phase 4: Preliminary Design and Land Acquisition Procedures

 

Preliminary Design

Autumn2003

Land Acquisition Mapping

Autumn 2003

Statutory Planning Procedures/ Environmental Impact Statement

Winter 2003

Oral Hearing (if required)

Summer 2004

Phase 5: Construction Documents Preparation/Tender Award

 

Document Preparation

Winter 2004

Tender Award

Summer 2005

Phase 6:Scheme Construction

 

Road Open

Winter 2007

The completion dates shown in this indicative programme are dependant upon the availability of funding from the National Development Plan

SCHEME FACT SHEET

(Note: This fact sheet is based on the proposal which went on public display in May 2002. Adjustments, if any, arising from submissions made during the public consultation period, will be published when the Route Selection Report has been finalised).

Scheme Length

12.9 km on east side of Enniscorthy 8.2 km on west side of Enniscorthy

Proposed Cross Section

Dual Carriageway on east side of Enniscorthy Single Carriageway on west side of Enniscorthy

Estimated Capital Cost

100 million euro

Proposed Junctions (more exact details of junctions will be confirmed during the preliminary design stage)

Junction on N30 (G) Junction on R702 (F) Junction at N80 and N11 north (E & I) Junction on R744 (J) Junction on N11 south (D)

Major Structures

15 Road Bridges 1 Rail Bridge (at Solsborough) 2 River Bridges (River Urrin & River Slaney)

 