The programmed dates for progression of the scheme are as follows:
|
Phase 1: Overall Project Planning | Complete |
Phase 2: Constraints Study | Complete |
Public Consultation II (Constraints and Route Corridors) | 20 th April 2001 & 10th May 2001 |
Publish Constraints Study Report | June 2001 |
Phase 3: Route Selection | |
Public Consultation III
(Preferred Route)
| 27th to 31st May 2002 |
Finalise Route Selection Report | Autumn 2002 |
Phase 4: Preliminary Design and Land Acquisition Procedures | |
Preliminary Design | Autumn2003 |
Land Acquisition Mapping | Autumn 2003 |
Statutory Planning Procedures/
Environmental Impact Statement
| Winter 2003 |
Oral Hearing (if required) | Summer 2004 |
Phase 5: Construction Documents Preparation/Tender Award | |
Document Preparation | Winter 2004 |
Tender Award | Summer 2005 |
Phase 6:Scheme Construction | |
Road Open | Winter 2007 |
The completion dates shown in this indicative programme are dependant upon the availability of funding from the National Development Plan
SCHEME FACT SHEET
(Note: This fact sheet is based on the proposal which went on public display in May 2002. Adjustments, if any, arising from submissions made during the public consultation period, will be published when the Route Selection Report has been finalised).
Scheme Length |
12.9 km on east side of Enniscorthy
8.2 km on west side of Enniscorthy |
|
Proposed Cross Section |
Dual Carriageway on east side of Enniscorthy
Single Carriageway on west side of Enniscorthy |
|
Estimated Capital Cost | 100 million euro |
Proposed Junctions
(more exact details of junctions will be confirmed during the preliminary design stage) |
Junction on N30 (G)
Junction on R702 (F)
Junction at N80 and N11 north (E & I)
Junction on R744 (J)
Junction on N11 south (D) |
|
Major Structures |
15 Road Bridges
1 Rail Bridge (at Solsborough)
2 River Bridges (River Urrin & River Slaney) |
|