The programmed dates for progression of the scheme are as follows:

  • Scheme Length (Km): 14.6
  • Proposed Cross Section: Single Carriageway
  • Estimated Construction Costs (euro): 31,000,000
  • Major Structures:
    • 1 River Bridge (River Boro)
    • 1 Road Bridge (at Aughnakean)
  • Proposed Junctions:
    • 3 at-grade staggered junctions
    • 5 at-grade T-junctions
    • 1 roundabout

Phase 1: Overall Project Planning

Complete

Phase 2: Constraints Study

Complete

Public Consultation II (Constraints and Route Corridors)

19thApril 2001

Public Consultation III (Amended Route Corridors)

26thJuly 2001

Publish Constraints Study Report

July 2002

Phase 3: Route Selection

 

Public Consultation III (Preferred Route)

14thto 18thJanuary 2002

Finalise Route Selection Report

Summer 2002

Phase 4: Preliminary Design and Land Acquisition Procedures

 

Preliminary Design

Spring 2003*

Land Acquisition Mapping

Summer 2003*

Statutory Planning Procedures/ Environmental Impact Statement

Summer 2003*

Oral Hearing (if required)

Winter 2003*

Phase 5: Construction Documents Preparation/Tender Award

 

Document Preparation

Spring 2004*

Tender Award

Autumn 2004*

Phase 6: Scheme Construction

 

Road Open

Spring 2007*

 

 

*The completion dates shown in this indicative programme are dependant upon the availability of funding from the National Development Plan

 