Future Programme

The budget allocated to this project for 2002 will ensure that the Route Selection Report can be finalised. Without allocations at this time for future years it is not possible to accurately predict a programme for the project. However, it may be helpful to have an indicative timetable and this is shown as follows:

Phase 1: Overall Project Planning

Complete

Phase 2: Constraints study

Complete

Phase 3: Route selection

Now complete

Phase 4: Preliminary design + land acquisition procedures

  • preliminary design
  • Land Aquisition Mapping
  • ststutory Planning Procedures/ EnvironmentalImpact Statement
  • Oral hearing (if required)

  • Autumn 2003*
  • Autumn 2003*
  • Winter 2003*
  • Summer 2004*

Phase 5: Construction documents preparation & tender award

  • Document preparation
  • Tender award

  • Winter 2004*
  • Summer 2005*

Phase 6: Scheme construction

  • Road Open

  • Winter 2007*

 

 

*The completion dates shown in this indicative programme are dependant upon the availability of funding from the National Development Plan

 